Airport Lighting Repair

Starting June 4th and ending June 18th, the south end 955 feet of the runway will be closed for Phase 1 of the long awaited major runway light repair. This partial closure is planned for 15 days. Phase 2 will be a 15 day partial closure of the north end of the runway from June 19th to July 4th, phase 3 will be a 5 day complete closure of the runway. Phase 3 Runway closure is scheduled from July 5th through July 9th. A second shorter runway closure will be scheduled for September or October.  This is an FAA Airport Improvement project that will replace the aging, non-functioning and corroding lights.